Project Outline:
Scope of work included compiling a comprehensive construction cost estimate for two greenfield high head hydroelectric power generation sites: Jimie Creek (66 MW) and Upper Toba (58 MW), located north of Vancouver on the B.C. Mainland.
The detailed estimate consisted of approximately 800 line items per site and was completed from the perspective of an EPC Contractor delivering a turn-key project. A cost estimate was also assembled using an EPCM delivery model for comparison of the relative cost of the two contracting methodology approaches.
- the installation of an owner provided eel ladder on the sloped west wall east of the raceway to the Varick Hydro Station.
Duration :
|
|
February - June 2010 |
Key Personnel: |
|
Ted Chant Richard McGivern Rafael Sanchez Damon Liu |
| Owner: |
|
Plutonic Power Corporation Murray G. Kroeker, P. Eng. Director of Engineering-Design (604) 669-4999 |
|
|
Last Updated on Tuesday, 13 July 2010 15:08 |