Clint Creek - Estimating Services Print

Project Outline:

  • 6.6 MW run-of-the-river project  at remote green field site on Vancouver Island, British Columbia
  • Estimated cost CAD $15,000,000.00
  • Estimate type class two per AACE 
  • Methodology used data assembled by trade along with a detailed quantity takeoff for concrete  / excavation / penstock / cofferdam / tunnel / transmission line / BOP and indirect costs
  • Estimate included provision of a means and methods review for  areas of high risk  such as tunnel, access roads and penstock
Project
Value:
 
$105,000.00
Duration :
  July - September, 2008
Key
Personnel:
  Ted Chant
Richard McGivern
Rafael Sanchez
Owner:   Brookfield Power
Owner Contact:   Peter Hellend
Project Manager, Hydro
(604) 661-9604