Clint Creek - Estimating Services |
|
|
Project Outline:
- 6.6 MW run-of-the-river project at remote green field site on Vancouver Island, British Columbia
- Estimated cost CAD $15,000,000.00
- Estimate type class two per AACE
- Methodology used data assembled by trade along with a detailed quantity takeoff for concrete / excavation / penstock / cofferdam / tunnel / transmission line / BOP and indirect costs
- Estimate included provision of a means and methods review for areas of high risk such as tunnel, access roads and penstock
Project Value: |
|
$105,000.00 |
Duration :
|
|
July - September, 2008 |
Key Personnel: |
|
Ted Chant Richard McGivern Rafael Sanchez |
| Owner: |
|
Brookfield Power
|
| Owner Contact: |
|
Peter Hellend Project Manager, Hydro (604) 661-9604 |
|
|
Last Updated on Friday, 18 June 2010 12:33 |